Construction Progress  

The construction phases of Wesal Project in Mokattam are based on a well-structured execution plan that adheres to the highest standards of quality and safety.

The process begins with excavation and site preparation, followed by the implementation of foundations using the latest engineering systems, and then the construction of the concrete structure with high efficiency. After that, work progresses to building and finishing stages using high-quality materials, with close attention to every detail under the supervision of a team of experts, ensuring the delivery of a fully integrated project that combines durability, sustainability, and modern design.

_

Excavation works are in progress

_
_

Casting the plain concrete raft foundation

_
_

Pouring reinforced concrete footings

_
_

 Currently pouring lower basement columns

_
Project completion rate 10%